Wind Power | Cimarron Wind Energy Project

The Cimarron Wind Energy Project is a 165MW wind powered generating facility in Gray County, Kansas. The facility is being developed by CPV Renewable Energy Company, LLC and is producing the electricity for the Tennessee Valley Authority (TVA).

The wind facility consists of 72 Siemens 2.3 megawatt turbines and they will supply TVA customers with renewable energy under a 20-year power purchase agreement.

Construction of the project began in December 2011 and financing for the construction was completed in January 2012 with the senior credit facilities provided by Bank of Tokyo Mitsubishi UFJ and Union Bank of California who acted as Coordinating Lead Arrangers and they were joined by Helaba, Siemens Financial Services and Lloyds as the Mandated Lead Arrangers for the $262.8 million.

The project will be sited on around 13,883 acres of private land under Easement Agreement with CPV and will interconnect to the Southwest Power Pool electric grid via the existing on-site 345-kilovolt Sunflower Electric Power Corporation transmission line that traverses the area.

Construction of the project is being carried out by Wanzek Construction, a MasTec Company, and will be operated by North American Energy Services.

“CPV is pleased to once again bring clean renewable wind powered generation to southwest Kansas,” said Sean Finnerty, CPV REC Sr. Vice President. “The Cimarron project adds to CPV’s growing asset base and will provide low cost, reliable wind generation to the Tennessee Valley Authority for years to come.”

Commercial operation for the project is expected to be achieved by November 2012.

Other Major Kansas Wind Energy Facilities

 

Project Name
Capacity
Location
Developer
Caney River
200MW
Elk County
Enel GreenPower
Elk River
150MW
Butler
PPM Energy
Flat Ridge I
100MW
Barber County
BP Alternative Energy / Westar Energy
Gray County
112.2MW
Gray County
FPL Energy
Meridian Way
105MW
Cloud County
Horizon Wind Energy
Meridian Way II
96MW
Cloud County
Horizon Wind Energy
Smoky Hills
100.8MW
Salina
TradeWind Energy
Smoky Hills II
148.4MW
Salina
TradeWind Energy
Solomon Forks
108MW
Thomas County
Acciona Energia
100.8MW
Dodge City
enXco

Wave Power | Wave Clapper and Power Wing

A new idea in wave power technology has been put to the test by Israel’s Eco Wave Power and it is hoped that when it is brought to a point where it may be commissioned it will be able to produce energy that is cheaper than a coal-fired power plant. The project is a wave energy harvest and conversion system and involves two proprietary float designs called the Wave Clapper and the Power Wing.

The difference between these devices and many of the other wave power devices that are in the process of being tested and further developed is that these devices can be installed on existing stable structures. This means that they may be placed on existing breakwaters, piers and floating platforms which means the cost of installation will be greatly reduced and many of the environmental impact studies will have already largely been performed.

A small scale proof of concept system has already been completed in a wave pool at the Hydro-Mechanical National Institute in Kiev and the company is now moving forward to a medium scale version.

The two different devices have been designed for a couple of different scenarios.

The Wave Clapper is a device that might be used where space is limited and it can be deployed in series to maximize the use of the available space. It is proposed that this device be placed with the floaters having very small spaces between one another.


Images: Eco Wave Power  

The larger Power Wing is able to operate in a more varying environment and is versatile enough to work efficiently at different wave heights. Not only that but it can also be adjusted so that the edge of the device is always parallel to the wave and this will ensure the maximum energy from each wave hits the float.

Part of the testing process for these devices involves working out the most effective configuration arrangements in which they might be deployed. This will change depending on the environment and surrounding wave conditions that are common to the area. Options such as straight or curved line configurations, staggered arrangements and placement of small floats behind larger ones are being assessed to take advantage of the different sea conditions.

To find out more about the storm protection mechanisms that have been built into these devices as well as the corrosion protection, shock-waves protection mechanism, lever regulation mechanism and other features you can visit the Eco Wave Power website.

Maintenance costs for the devices have been planned to be reduced to as low as possible by placing the oil tanks and pneumatic equipment on land. This means that not only will it be easier for repairs to be carried out but the risk of pollution will be reduced.

Testing of the medium sized Wave Clapper and Power Wing will begin within the next few months.

The Wave Clapper is designed with three different mechanisms that may be employed to protect the device during storms and rough conditions. These methods may either lift the device out of the water or submerge it until conditions improve.

Wind Power | Windstar Project

The Windstar Project is a wind farm that has been constructed in Tehachapi, California by Western Wind Energy Corp. The wind farm sits on 1,850 acres of land owned by the company and consists of 60 Gamesa G80 and G87 2MW turbines giving the project a maximum generating capacity of 120MW.

The company has signed a $204.5 million power purchase agreement with Southern California Edison to supply the output from the farm. It is planned that the project will be brought online in two stages with the first 106MW commencing by December 2011 and the last 14MW to be commercially operational in February 2012. At the time of writing this the last of the second phase of turbines have been erected and it is looking very likely that the project is on track for the expected completion date.

When the first phase of the project became operational it effectively doubled Western Wind’s operational wind energy capacity.

Wind Power | Michigan Wind 2 Wind Project

The Michigan Wind 2 Project has been commissioned by Exelon Wind in Minden City, Michigan. This wind farm consists of 50 Vestas Wind Systems turbines and has a maximum generating capacity of 90MW. It represents the first commercial wind project to have been developed by Exelon Wind.

As well as producing electricity for more than 30,000 homes in the area the wind farm is also going to be generating over $12 million in revenue for the area through local tax payments over a period of 20 years.

The developer has been purchasing wind projects over eight separate states and has a portfolio of over 750MW. The wind generation that the company owns in Michigan has now been increased to 212MW with the completion of this project. The project is located southeast of the already operational 46 turbine Michigan Wind 1 project in northern Sanilac and Huron counties. Exelon Wind also operates Harvest I Wind in Elkton, Michigan. In early 2012, Exelon Wind will begin construction on Harvest II Wind, a 59.4 MW project in nearby Pigeon, Michigan.

“We’re excited to bring Michigan Wind 2 online. The clean generation from this project will help Michigan meet its renewable energy goals, it will provide clean energy for over 30,000 homes and brings significant economic benefits to the local community,” said David Drescher, Vice President Wind Energy for Exelon Power.

Exelon Wind is a division of Exelon Power, which owns and operates Exelon’s renewable, hydroelectric and fossil power plants. Consumers Energy, based in Jackson, Michigan, is purchasing the output from Michigan Wind 2 through a 20-year renewable energy purchase agreement.

Advantages Of Solar Power

Solar energy is still a developing energy with technological advances continually being made to make it more cost efficient and more abundant. Currently it is still a form of electricity that is only used by a minority of households, either as self-contained rooftop installations or on the grid direct from a solar power plant.

There are still pockets of opposition to the development of more solar farms with the main criticism being that it is a very expensive way to create electricity. While this is true compared to the traditional use of fossil fuel such as coal, if you take a wider view and compare the cost with what it is saving the world in terms of non-renewable resources you could say that the extra dollars are a small price to pay.

There are definitely advantages to using solar power and some of these advantages are more important to some people than others. Here is a brief list:

  • Solar energy is a renewable energy source. This means that no matter how much sunlight or heat we use to create electricity it won’t be exhausted.
  • The creation of electricity does not disrupt neighboring residents. This is a completely silent process.
  • Creating electricity from solar power does not produce pollutants, unlike coal-based electricity.
  • Electricity from solar panels can be generated in locations that are isolated from an electricity grid without the need to run electricity cables all over the place.
  • Solar power gives you the potential to become completely independent from a utility company.
  • Over the long term you can save money on your power bill, in some cases not only will you no longer have to pay for your electricity, if you generate enough the power company could pay you for the excess electricity added to the grid.
  • Once installed solar panels and solar cells don’t require any maintenance.
  • Apart from the sun, solar energy requires no fuel.
  • Your hot water bill will be greatly reduced after the installation of a thermal hot water system.
  • With the development of CSP, it is possible to continue producing electricity from solar energy after the sun has gone down, or on cloudy days.
  • Solar power can be used by a wide range of devices as well as for the production of electricity to power your home. Lights, watches, calculators, cars can all be powered by solar energy.

As was pointed out earlier, some people may not feel as though all of these solar power advantages are applicable to them. But every single person is affected by the increase of power that is generated by a means that reduces the amount of pollution that is pumped into the atmosphere. Forget about talks of the Greenhouse Effect and global warming, our immediate health can be improved by the closure of one power plant that burns coal to generate electricity.

Benefits of Solar Energy

In order to justify why there is so much technological and monetary effort going into solar power and the development of new solar energy facilities it might be worthwhile going over a few of the significant benefits that are achieved from using solar energy. Some of these may seem obvious, some may be debatable and some may be surprising to some, but make no mistake, regardless of the detractors, solar energy is a valuable resource to develop and to refine.

So here are 10 benefits of solar energy.

1. Solar energy is not only sustainable, it is renewable and this means that we will never run out of it. It is about as natural a source of power as it is possible to generate. Not only are we able to refuel our vehicles with it we can heat our water and light our homes.

2. We can generate our own source of electricity via solar panels potentially enabling us to live off grid. In other words we need not be dependent on the public utility companies to supply our power and we also won’t be required to pay for out power.

3. The creation of solar energy requires little maintenance. Once the solar panels or troughs have been installed and they are brought up to maximum efficiency there is little else to do to ensure they are in working order.

4. They are a silent producer of energy. There is absolutely no noise made from photovoltaic panels as they convert sunlight into usable electricity.

5. The creation of solar power is unobtrusive, particularly the solar electricity that is generated from photovoltaic panels that sit on top of the roofs of buildings.

6. Many governments around the world and locally offer generous rebates and monetary incentives to install solar panels and solar hot water systems. The governments of various nations understand the importance of the creation of electricity from renewable sources is to the entire world and are receptive to making it as attractive a proposition as possible for individuals.

7. If you produce enough solar electricity or if you don’t use all of the electricity that you produce you can sell it back to the utility company for electricity credits. This is a rare occurrence for the most part, unless you are away on vacation for a week or two, in which case your solar panels will go on producing electricity that you won’t be using.

8. Large solar energy facilities can produce electricity regardless of whether the sun is shining or not making them sustainable and reliable electricity producers. The solar power plants capable of achieving this feat are generally thermal solar power producers capable of storing the heat generated and using it when the sun is not shining.

9. The advancements in technology used to create solar energy are continuing to improve making it even more cost effective. As it becomes cheaper to install new solar energy generators the price of solar electricity will continue to drop bringing it more into line with traditional, fossil-fuel generated electricity.

10. Solar electricity power plants and personal solar panels produce zero emissions and make no adverse mark on the environment.

Biomass | Lufkin Power Plant

Work has started on the construction of the first biomass power plant in the state of Texas. The groundbreaking ceremony for the start of the project has just taken place hosted by Aspen Power in Lufkin, Texas.

The Lufkin Biomass Power Plant will have a maximum capacity to produce 50MW of renewable energy sourced electricity. The facility will be fuelled by 525,000 tons of logging and wood debris each year. It is reported that Lufkin and surrounding areas currently produces up to 600,000 tons of wood waste each year, so the facility will be helping to solve an existing waste problem.

The facility will provide enough power for the city of Lufkin and will provide 160 new jobs for the local community.

Early opposition for the Lufkin Biomass power plant came from members of the local community, but thanks to a public relations campaign by Aspen Power, the residents of Lufkin were reassured as to the benefit to the community and to the low environmental footprint such a biomass facility would leave.

It is expected that construction of the Lufkin Biomass Power Plant will be completed by October 2009.

Wind Power | Fire Island Wind Project

Up until this point the total wind energy capacity in the state of Alaska comes to somewhere approaching 10MW with the 4.5MW Kodiak Island Wind Project making up a significant proportion of that. That is about to be significantly increased thanks to a power purchase agreement signed in October 2011. Chugach Electric Association (CEA), Alaska’s largest electric utility, agreed to terms with Cook Inlet Region Inc. (CIRI) to purchase the energy produced by the 17.6-MW Fire Island Wind Project, allowing the project to move closer to completion.

According to Jim Jager, CIRI corporate communications director, the project began in the 1990s when CEA tried to diversify its power generation portfolio. CEA was interested in wind energy as an alternative to natural gas and conducted a survey of south-central Alaska to identify the best potential wind sites. Fire Island quickly rose to the top of the list because of proximity to the load center, land availability, lack of conflicting land uses, and a relatively low risk of potential environmental impacts.


Wind turbine foundations
Image: Fire Island Wind, LLC

“As you go down the checklist, Fire Island is a very attractive site. CIRI owns the majority of Fire Island, so CEA approached CIRI and asked if we would be interested. We said yes. That’s when the Fire Island Wind Project was born,” Jager said.

Soon after, anemometer tests to determine the strength of the wind resource commenced. According to Jager, around this time CEA’s board members changed and the utility dropped out of the project. At that point, CIRI proceeded on its own to search for project funding.

CIRI qualified for $19 million in funding through a Section 1603 American Recovery and Reinvestment Act tax credit for the project and $25 million of state grant funding for submarine and mainland transmission infrastructure that would link the wind farm with the Anchorage electrical grid. CIRI began preliminary construction, but before the project could move forward, the project had to overcome many hurdles, including finding a utility to purchase the power, demonstrating that the integration of wind into the relatively small Alaska grid would not impact power quality, and obtaining approval from the Regulatory Commission of Alaska.

Although many of the local utilities and power cooperatives were initially apprehensive about how 17.6 MW of wind energy would be integrated into the power grid, CIRI was able to ease those concerns with support from the National Renewable Energy Laboratory (NREL).

According to Brian Hirsch, senior project leader for NREL’s Alaska initiative, the lab’s role in the project was to provide technical assistance and analysis on grid stability and integration issues and resource assessment verification. Primarily through NREL, the Department of Energy Wind Program has provided technical support for the deployment of wind technologies in Alaska for more than 10 years, including direct funding to the Renewable Energy Alaska Project that has worked to support projects like Fire Island and other renewable energy activities across the state. The Fire Island project has been a long-term goal of the Alaska Wind Working Group, which works to educate stakeholders about using wind energy in the Last Frontier.

Once the technical concerns were alleviated, power purchase negotiations continued until CEA signed on to purchase the energy at a flat net price of $97 per megawatt-hour for 25 years beginning on January 1, 2013. The project is expected to supply approximately 4% of CEA’s electric load. Although the cost of energy for consumers will be slightly higher than the current average price, the flat rate is expected to make the cost more attractive as gas and power prices increase in the future. In its October 10 ruling, the Regulatory Commission of Alaska approved the project, indicating that the project is a good way to support the Alaska Legislators’ push to expand the use of renewable energy at a very minimal cost to CEA’s members. The true benefit of the project will be determined over time based on the actual cost of future natural gas prices and the real costs of the operational integration of the wind farm.

The project will feature 11 GE 1.6-MW turbines configured for the Arctic environment and will cost approximately $65 million, which Jager credits to a combination of events.

“Right now there’s a bit of an oversupply of wind turbines on the market, so that decreases the prices of the equipment,” Jager said.

Jager also said that the project was able to take advantage of the tax credit for renewable energy projects and that due to the state of the economy, construction companies are willing to bid lower on project contracts than a few years ago.

“The confluence of those three events has helped to keep the cost of this project down,” he said.

The Fire Island project will employ between 100 and 120 workers during construction, with on-island workers numbering between 80 and 100 at any given time. Though on-island work won’t resume until Cook Inlet is ice-free again in April 2012, plans call for shore-side construction work on transmission infrastructure in the near future. Jager expects to generate the first power in the beginning of September 2012, with the project online soon thereafter. Six permanent positions will be created for the operation and maintenance of the facility.

Although a great deal of time has been devoted to bringing this project closer to fruition, the delay was not the result of a lack of support from the local community.

“The community support has been overwhelming. We’ve done public polling that shows that in excess of 80% of the public supports the idea of diversifying with Fire Island Wind Power. A significant majority, more than 70%, said they would be happy to pay an extra $2 a month, if that’s what it takes, to bring Fire Island to generation,” Jager said.

The involvement of DOE and Wind Powering America was initiated early in Alaska, primarily focused on the implementation of wind technology in rural parts of the state.

“Fire Island has been a very interesting project since it was envisioned,” said Ian Baring-Gould, Wind Powering America’s national technical director. “Not only is the project situated right off the coast of Alaska’s most populous city, it is right off the flight path for Ted Stevens International Airport and will serve as another clear example of how the state is working to obtain 50% of its electric generation from renewable and alternative sources by 2025, becoming a living example of the state’s motto, ‘North to the Future.’ This project also clearly demonstrates how over time organizations with differing goals and responsibilities can work together to implement a new technology such as wind. The integration of wind into the Alaskan Railbelt grid is not a trivial issue, and it required the technical collaboration of many organizations and individuals. The leadership and staff of Chugach Electric should be commended for their efforts, as should the leaders of CIRI, who have worked tirelessly, and at times against seemingly insurmountable odds, to get this project this far.”

According to Hirsch, Fire Island Wind Project is an important step for Alaskan wind energy as a whole.

“Fire Island is opening the door for large-scale renewable energy on the Railbelt, both for Independent Power Producers and utility-led projects. We’re already seeing some additional development as a result of it in terms of other large-scale wind projects,” Hirsch said.

Wind Power | Spearville 3 Wind Energy Project

It is expected that construction will start on a wind power project 17 miles northeast of Dodge City, Kansas in the first quarter of 2012. This is a 100.8MW wind farm that will be known as the Spearville 3 Wind Project and it will be developed, built and owned by enXco with expected completion of the project and commissioning to take place by December 2012.

An important step has already taken place which should help assure the viability of the project. A 20 year Power Purchase Agreement (PPA) has been entered into between enXco and KCP&L. This agreement was finalized in November 2011.

The wind farm will consist of 63 General Electric XLE turbines each of which is rated at 1.6MW.

“The project’s proximity to other enXco developed wind facilities, along with near-term constructability and advanced development status, allows both development and transmission synergies,” said Tristan Grimbert, president & CEO of enXco. “We look forward to once again delivering a successful project to our utility partner who has demonstrated both trust and confidence in the EDF EN Group to deliver wind projects and diversify their generation portfolio.”

“In this region of the country, wind is an abundant renewable resource. We believe that pursuing wind energy development at this time will bring the benefits of that resource to our customers,” said Terry Bassham, president and chief operating officer of KCP&L.

The Spearville 3 Wind Project will join the existing Spearville Wind Farm which has been in operation since 2006 and has a maximum generating capacity of 100.5MW. This particular facility consists of 67 General Electric 1.5MW turbines.

This new project will join a growing list of large wind farms that have been developed and are operational in Kansas. Displayed below is a table that lists the largest wind farms in the state.

Other Major Kansas Wind Energy Facilities

 

Project Name
Capacity
Location
Developer
Caney River
200MW
Elk County
Enel GreenPower
Cimarron
160MW
Gray County
CPV Renewable Energy
Elk River
150MW
Butler
PPM Energy
Flat Ridge I
100MW
Barber County
BP Alternative Energy / Westar Energy
Gray County
112.2MW
Gray County
FPL Energy
Meridian Way
105MW
Cloud County
Horizon Wind Energy
Meridian Way II
96MW
Cloud County
Horizon Wind Energy
Smoky Hills
100.8MW
Salina
TradeWind Energy
Smoky Hills II
148.4MW
Salina
TradeWind Energy
Solomon Forks
108MW
Thomas County
Acciona Energia

Wind Power | NaiKun Offshore Wind Energy Project

The first offshore wind energy project to be developed in Canada’s waters may soon become a reality after British Columbia-based renewable energy company NaiKun Wind Energy Group and the Council of the Haida Nation formed a partnership that will operate and maintain the NaiKun wind energy project after construction.

The NaiKun project is to be located in British Columbia’s Hecate Strait, between the mainland and the Haida Gwaii, also known as the Queen Charlotte Islands. The area is the traditional territory of the Haida, the indigenous people of the area.

The agreement provides benefits to the Haida Nation from the project, including revenue sharing, environmental stewardship and employment and economic development opportunities.

Construction on the project is expected to begin in 2012. The project could have up to 110 turbines, installed off the east coast of Haida Gwaii. Energy generated from the turbines will be collected at an offshore substation in the center of the project and converted into electricity, which will be transmitted to the mainland by a subsea cable. NaiKun’s proposal was to provide up to 396 megawatts of electricity, or enough to power approximately 130,000 homes.

The project is contingent upon receipt of environmental approvals from the Haida Nation and through the harmonized federal/provincial environmental assessment process, and the award of an Electricity Purchase Agreement from BC Hydro.

Features of the project include the following:

Proven Technology:

- Wind energy is one of the cleanest, most abundant and cost-effective resources for electricity generation. Wind speeds over water are generally greater than on land which makes the energy from offshore wind projects more consistent and efficient. Offshore wind projects similar to NaiKun’s are successfully operating in Europe and several are being considered throughout North America.

- NaiKun recently signed a letter of intent with Siemens Wind Power regarding the supply of up to 110 wind turbine generators. Turbines will be installed in 2013 and 2014. Siemens Wind Power is a global leader in the development and installation of wind power solutions with more than 7,000 installed turbines.

- NaiKun has also signed a memorandum of understanding with Siemens Canada Limited’s Power, Transmission and Distribution Division for the transmission components of the project.

Superior Wind Resource and Favourable Site:

- Hecate Strait has some of the strongest, most consistent winds in Canada. Based on data collected, the NaiKun project site is located within an area with mean annual wind speeds between 9.5 and 10 metres per second. The actual mean wind speed during the first full year of measurement was 10.1 metres per second. This region has the potential to become one of the most efficient and high-producing wind project locations in the world.

- The shallow and sandy seabed at the NaiKun project site is well suited to offshore construction. As well, additional project phases can be implemented as needed to meet the future energy needs of British Columbians. This proposal covers the first of five phases for the wind power development.

“The Haida people support development that brings benefits of all kinds – individual, commercial and environmental – to Haida Gwaii and to the Haida Nation,” said Guujaaw, president of the Haida Nation. “We fully believe that, subject to confirmation of environmental feasibility, this offshore project will bring significant long-term benefits to the Haida Nation. For these reasons we are proud to be participants in the project.”

NaiKun Chairman Michael C. Burns said, “This agreement is the result of many years of working together and it reflects the commitment from both partners to move this project forward. NaiKun will gain from the knowledge and insight of the Haida and welcomes the thoughtful support of the Nation and its leaders.”

Next Page »